Collingwood Podcast Studio Fitout: The Resilience Project

The Resilience Project

QTC Build completed a commercial office fitout in Collingwood for The Resilience Project, a mental health and wellbeing organisation, and their affiliate The Imperfects Podcast. With an accelerated design programme completed before Christmas, construction was undertaken throughout the Christmas shutdown to meet an already compressed timeframe. When the client’s lease expiry brought the move-in date forward by a further week, QTC Build adjusted the programme and successfully delivered a purpose-built podcast recording studio, two recording booths, meeting rooms, a boardroom and open-plan workspace ahead of the revised deadline.

The Brief

The Resilience Project, a leading Australian wellbeing and education organisation, engaged QTC Build to transform a warm shell tenancy in Collingwood into its new headquarters. The fitout centred around a purpose-built podcast studio for The Imperfects Podcast and included two additional recording booths, meeting rooms, a boardroom and collaborative open-plan workspaces.

The project commenced under an accelerated design programme before Christmas, with construction carried out throughout the Christmas shutdown to meet a compressed timeframe. During construction, the client’s lease expiry brought the required handover date forward by a further week, requiring the programme to be revised while maintaining the same quality and scope.

The Challenge

The podcast studio was the most technically demanding aspect of the project. Professional recording required genuine acoustic isolation, so QTC Build researched the studio’s operational requirements and developed a cavity wall system comprising separated wall frames, acoustic insulation and internal acoustic treatments to achieve the required acoustic performance.

Construction also had to be carefully coordinated to minimise disruption to neighbouring tenants. Much of the noisier work was undertaken before and after standard business hours, adding further complexity to an already compressed programme delivered over the Christmas shutdown.

The Approach

QTC Build managed the complete design and construction process, delivering a purpose-built podcast studio of approximately 50m² together with two additional recording booths for individual recording sessions.

The remainder of the tenancy was configured with meeting rooms, a boardroom and collaborative workspaces, while existing furniture was retained and reconfigured where practical to maximise value and reduce unnecessary waste.

Construction activities were carefully programmed around neighbouring businesses, allowing progress to continue throughout the Christmas period while minimising disruption. Despite the accelerated timeframe and revised handover date, QTC Build completed the project one week ahead of the client’s required move-in, providing valuable time for The Resilience Project to settle into its new workplace before operations commenced.

The Result

The Resilience Project successfully relocated into its new Collingwood headquarters with a purpose-built workplace tailored to its operations. The podcast studio has performed exactly as intended, providing a professional recording environment with effective acoustic isolation for The Imperfects Podcast.

QTC Build’s commitment extended beyond practical completion. On the evening before the first podcast recording in the new studio, our team returned after hours, at no cost, to help install the client’s acoustic baffles and complete the final studio setup. With recording scheduled for the following morning, we wanted to ensure everything was ready so the team could begin using the new studio without delay. It was a simple gesture that reflected our commitment to our clients long after the construction works had been completed.

The project also established a strong relationship with the building owner through proactive stakeholder management, clear communication and a collaborative approach throughout construction. Following completion, the owner recommended QTC Build to other tenants within the building and engaged us to undertake additional base building works and tenancy splitting projects. That relationship has since led to multiple further projects within the building, demonstrating how quality delivery and trusted relationships continue to generate opportunities well beyond the original project.

Andy was exceptional to work with in every aspect, and we really appreciated his genuine commitment to doing the best job possible. It is the first building project I have been involved in that finished ahead of schedule.

– Ben Waterman

Project Snapshot

Client Type

A leading wellbeing and education organisation.

Location

Collingwood, Melbourne

Project type

Warm Shell Office, Podcast Studio

Scope

Podcast studio (approx 50m²), 2 recording booths, meeting rooms, boardroom, workplace area

Added service

Acoustic Design, Fast-track Design and Build timeline

Have a project in mind?

Watch the Video

Watch the Series

  • Week 1 – Pre Construction

  • Week 2 – Wall Framing

  • Week 3 – Rough-In

  • Week 4 – Sheeting

  • Week 5 – Ceilings & Services

  • Week 6 – Plaster & Paint

  • Week 7 – Finishes & Glazing

  • Week 8 – Handover

Brands we use

    Next steps

    Need a fitout built to a fixed deadline?

    Related Projects

    • Breakout lounge with green sofa and biophilic planted screen, Clinibase office fitout, Collingwood.
      Collingwood, Melbourne, VIC

      Clinibase Healthcare Recruitment Fitout

      A two-stage Collingwood office fitout across two floors, relocating 103 workstations and expanding into a second level six months ahead of plan.

      View Project
    • Podcast studio with lighting rig, cameras, leather sofa and yellow armchair at the Empower Wealth office fitout, North Melbourne.
      North Melbourne, VIC

      Empower Wealth Advisory Office Fitout

      A 700m² warm shell office fitout in North Melbourne featuring a bespoke kitchen, operable conference wall, podcast studio and collaboration spaces, delivered ahead of a major corporate event.

      View Project
    • Breakout zone with brown armchairs on a round rug beside open-plan desks, CPB Contractors office fitout, Blackburn North.
      Blackburn North, VIC

      CPB Contractors Satellite Office Fit Out

      A satellite office fitout for CPB Contractors supporting the Tram Road to Springvale Road Big Build project, delivering 126 workstations with a strong sustainability focus.

      View Project